Previous | Table of
Contents
Implementation
Vessels
The new standby vessel arrangements were implemented in September
1996. The mother vessel is positioned at the geographic center of
the circular guardzone. The mother vessel supports all the installations
manned that day within the guardzone. The radius of the guardzone
changes, depending on the prevailing wind and sea conditions; but
is taken no greater than 10 nautical miles. The vessel master, who
is the sole arbiter as to the size of the guardzone, must set his
support circle to meet the set performance standards, which as stated
earlier are based on time to rescue or arrival at the scene of an
emergency.
Where the number of workfronts is such that the mother vessel cannot
support them all, additional standby vessels of the conventional
type are used. These conventional vessels are also assigned to a
guardzone but in order to meet the set performance standards, their
guardzone radii are limited to 5 nautical miles.
Compared with a conventional standby vessel, the mother has the
following additional hardware.
- Two 34 ft daughter craft each with their own Personal Locator
Beacon (PLB) direction finding sets and visual display units to
show the locations of the personnel to be rescued.
- Two sets of heave-compensated Caley Davits.
- Radar receiver to accept field radar information from the radar
system set up on one of the manned complexes. This allows the
master of the mother vessel to have a radar horizon in excess
of 20-30 nautical miles from the vessel, which is far in excess
of what can be achieved using the standby vessels own radar
system.
When a Personal Locator Beacon (PLB) is activated either by contact
with seawater or manually triggered, the unit sends a VHF signal
to a pre installed booster unit on the installation that the person
has just left. This information is immediately re-transmitted on
UHF to the mother vessel master, whose computer displays a course
to steer and a time to intercept.
When the daughter craft comes within 0.6 to 2 nautical miles of
the person in the water, it switches to its own VHF direction finder
set for better accuracy when finally homing in on the person in
the sea.
In this implementation, the mother vessel has a sister ship with
identical software and hardware, including Caley davits, available
to accept the daughter craft when necessary. The daughter craft
are swapped over when one or other vessel needs to go out of the
field for maintenance. When both vessels are in the field, one is
used as the standby vessel and the other is used as an in-field
supply vessel.
The current limitations set by the Marine Safety Agency for daughter
craft operations are:
- The daughter craft should not operate at more than 10 nautical
miles from the mother vessel.
- The daughter craft should not be operated in seas greater than
3.5 meters significant height.
- The daughter craft should not continuously operate for more
than 4 hours with a 3 man crew or 8 hours with a additional coxswain.
Platform-based radar system
A platform-based radar system was installed on one of the manned
complexes to provide the mother vessel master with continuous warning
of approaching vessels. The height of the radar antenna allows the
mother vessel master to have a radar horizon in excess of 20-30
nautical miles, depending on weather conditions. This is much better
than can be achieved with the lower antennas on standby vessels,
especially in rough seas. Moreover, the platform-based system has
automatic processing and alarm capabilities, reducing the need for
human vigilance. The mother vessel master receives cleaned
up images of vessels moving within and converging on the field.
The speed and direction of each vessel is displayed with a predicted
time to impact if apparently on a collision course. Procedures are
in place on all the installations defining the actions to be taken
if a vessel is on a collision course.
Work planning systems
In order to facilitate the correct deployment of the mother vessel
and the most economical utilization of the sister vessel, the Operators
work planning system was integrated with new software capable of
optimizing the sharing arrangements for the mother vessel and its
sister vessel. This information is sent live down a
telephone link to the mother vessel master. The system records all
operating envelopes and vessel movements for that day.
Sea trials
The purpose of the trials was to demonstrate that the chosen hardware
and software could be integrated in an offshore environment to deliver
a total system that offered effective arrangements, a good prospect
of recovery and which maintained or improved on existing arrangements.
The trials set out to simulate a number of foreseeable emergency
events.
- the rescue of persons from a platform spider deck;
- the rescue of a close knit group of people from the water as
per helicopter ditching;
- the rescue of a single person representing someone falling overboard;
- the rescue of a number of persons in the water who have become
dispersed.
The trials were carried out in April 1996 and witnessed by the
Health and Safety Executive and by the Operator and various contractors
involved in the implementation of the system.
The results showed that the systems functioned well and that the
defined Performance Standards can be met. In addition, areas for
improvement were identified and incorporated into the commissioning
trials held in September 1996.
Vessel commissioning trials
Trials were carried out in September 1996 to demonstrate that the
vessels, their crews and the offshore and onshore support staff
had reached a sufficient level of competency to fully support each
of the performance standards.
The trials undertaken related to the following scenarios:
- ditched helicopter in the guardzone, day time;
- normal operational support escape from a not normally
manned installation;
- overside working person overboard at night during planned
work activities.
Ditched helicopter
The sea conditions for these trials were rough with wave heights
of 4 meters and wind speeds gusting between 20 to 30 knots. Twelve
dummies representing 10 passengers and two crew were deployed, each
with a PLB, to simulate a helicopter ditching. At this point the
mother vessel was situated 4.5 nautical miles from the incident.
The first dummy was recovered by a daughter craft after 15 minutes
(the performance standard is 20 minutes or less). All twelve dummies
were recovered after 35 minutes. This is an average pick up time
per survivor of 1.6 minutes in relatively heavy seas.
Man overboard
Sea conditions were moderate with wave heights of 3.5 meters A
daughter craft was deployed in the water approximately 800 meters
from the platform. The alarm signal from the PLB was registered
almost immediately. The daughter craft went directly to the dummy
in the water and the dummy was recovered to the daughter craft within
2 minutes from entering the water. The daughter craft was recovered
to the mother vessel within 10 minutes of starting the trial.
Evacuation
For this exercise ten dummies, each with a PLB, were placed into
the sea at short intervals to simulate the uncontrolled evacuation
of a typical not normally manned installation by its maximum complement
of 10 persons.
Weather conditions were moderate with 3 meter waves, tide 0.7 knots
and wind speed of 20 to 24 knots. The emergency signals from the
PLB's were transmitted to the mother vessel almost immediately.
A daughter craft was launched with a course to steer and estimated
time of arrival. The daughter craft traveled at speeds of 34 to
36 knots towards the incident. At approximately 1.5 nautical miles
from incident the onboard direction finding equipment locked on
to the strongest PLB signal which in turn led the daughter craft
to the first man in the water. This dummy was recovered
within 22 minutes of the first alarm signal. All ten dummies were
recovered within 28 minutes of this alarm. The longest time a dummy
was in the water was 23 minutes. The dummies had drifted 400 to
500 meters from the platform and were dispersed over an area of
100 meters diameter.
Top
Conclusions
The mother/daughter standby vessel arrangements were implemented
in September 1996. They were demonstrated by risk assessment, and
later proved by trials, as capable of maintaining or improving safety
levels while reducing the number of standby vessels required to
support the installations in the field.
Acknowledgments
Sea Marshall Rescue
Systems Ltd developed the Personal Locator Beacons mentioned
in this article. Method Computing
developed the software for planning the daily standby vessel sharing
operations. SafeMarine
integrated radar, PLB's, direction finding equipment and other hardware
and software into a complete electronic system for managing standby
vessel operations and co-ordinating rescure operations.
Previous | Table
of Contents | Top
|